Things to Consider
For Your Boiler Rental

Cleaver-Brooks Boiler Rental Fleet

Our rental fleet has boilers starting at 5HP with operating pressures starting at 15PSI,
and watertube units starting at 20,000 PPH. Multiple boilers can be used in parallel
to meet steam demands higher than the capacity of a single boiler.


Download a copy of the things that you should consider before you make your boiler rental.

Download  

Boiler Size and Weight

Boiler sizing and weight varies depending on each rental. Sizes starting at 23" c 27" x 46" and up.

Capacity (W, H, L) Shipping Dimensions Shipping Weight Operating
100 hp 8' x 14' x 30" 30,000 lbs 45,000 lbs
200 - 300 hp 8' x 14' x 30" 45,000 lbs 60,000 lbs
350 - 600 hp 8' x 14' x 30" 50,000 lbs 65.000 lbs
20 - 40,000 lb/hr 10' x 14' x 50" 60,000 lbs 80.000 lbs
40 - 60,000 lb/hr 10' x 14' x 50" 80,000 lbs 100.000 lbs
75 - 100,000 lb/hr 12' x 14' x 30" 100,000 lbs 125.000 lbs
150,000 lb/hr 10' x 16' x 40" 130,000 lbs 160,000 lbs

Temporary boilers requires a firm foundation or footing. A concrete pad is the best support and asphalt is an acceptable alternative. At a minimum, a stable, well drained, compacted area is required with wood timbers sufficient to support the boiler's weight. The boiler must be blocked-up prior to operation. All weight must be removed from the running gear on trailer-mounted boilers.

Fuel Type (natural gas, #6 fuel Oil, #2 fuel oil)

Type of Fuel Supply Pressure
Natural Gas 15 psig regulated
No. 6 Fuel oil 150 psig regulated
No. 2 fuel oil 150 psig regulated and heated to 200" (approximately)

Power Requirements

Type of Fuel Power (480VAC, 30, 60HZ)
5 - 10,0000 lb/hr 50 Amps
10 - 20,000 lb/hr 75 Amps
20 - 40, 000 lb/hr 100 Amps
40 - 65,000 lb/hr 150 Amps
65 - 1000.000 lb/hr 200 Amps
100 - 150,000 lb/hr Consult C-13

A disconnect switch must be provided between the power source and the rental boiler. Temporary conduit and wiring should be installed after rental boiler arrives at the site.

Piping Size

Piping size varies depending on each rental.

150 PSI Steam

Capacity Steam Line Natural Gas Fuel Oil Feed Water Blowdown
10,000 lb/hr 4" 2" .75" 1" 2"
20,000 lb/hr 6" 2.5" .75" 2" 2"
30,000 lb/hr 6" 3" .75" 2" 2"
40,000 lb/hr 8" 3" .75" 2" 2"
50,000 lb/hr 8" 3" 1" 2" 2"
60,000 lb/hr 8" 3" 1" 3" 2"
75,000 lb/hr 8" 4" 1.5" 3" 2"
100,000 lb/hr 10" 6" 2" 4" 2"
150,000 lb/hr 12" 6" 2" 4" 2"

650 PSI Steam

Capacity Steam Line Natural Gas Fuel Oil Feed Water Blowdown
30,000 lb/hr 4" 3" .75" 2" 2"
40,000 lb/hr 6" 3" 1" 2" 2"
50,000 lb/hr 6" 3" 1" 2" 2"
60,000 lb/hr 6" 3" 1.5" 3" 2"
75,000 lb/hr 8" 6" 2" 4" 2"
100,000 lb/hr 8" 6" 2" 4" 2"
150,000 lb/hr 10" 6" 2" 4" 2"

All connections, 1.5 and larger, should be flanged. All Piping should be ASTM A -106 Gr. or A-53 Gr. B, SCH 80 or equivalent.

Instrument Air

On larger boilers, instrument air is required to drive the dampers, combustion controls, valves and regulators. Generally, a supply of 1-2.5 SCFM of Dry, clean instrument air regulated to 20-25 psig is sufficient.

Weather Protection

Generally, all rental boilers are equipped with weather protection. However if low temperatures, are expected, provisions should be made to protect the boiler room from freezing. A shelter in front and around the boiler should be considered for the comfort of the operating personnel during inclement weather.

Local Codes

Check local codes for local stack height restrictions, emission limits and other boiler installation requirements.

Get professional custom support